中文 English
Welcome to Gwas Power! Today is 05/03/2025
Sitemap Favorite Online

QR-Code call
News
Recommend Products
Contact Us

Gwas Power
Service Call:+86 028-65526686
Phone:+86 028-65526686
Mobile:+86 151 8448 7333
E-Mail:chinagewasi@163.com
Web:www.china-gwas.com.cn
Address:Building 32, No. 567 Boshi Road, Shou'an Street, Pujiang County, Chengdu City, Sichuan Province.
Workshop:Room 616-618, Block B, Building 2, Wukuai Stone Central World, Jinniu District, Chengdu City, Sichuan Province.

You are here: Home » News » FAQ » The installation of diesel generator set shall be carried out according to the following procedures:

The installation of diesel generator set shall be carried out according to the following procedures:

Author:Gwas Power  Click:1631 Published:2025-05-03
1. After the basic test has passed , the unit can be  installed. 
2. An installed genset needs to level and solidify the bottom mattress.

3. Installation of oil, gas, water cooling, wind-cooling, smoke gas emission and other systems and insulation noise protection facilities is completed. 

As well as fire protection equipment configured as required, the static test of the generator and the line inspection of the random distribution control cabinet are passed, 

the generators can be tested in empty space;

4. Generator empty test operation and test adjustment qualified in order to load test operation;
5. After the continuous faultless load test operation has passed, it can be put into standby.
Recommend News